January 28 Workday
/We had a good crew come out to the track today and work non-stop for hours at a time. One group was in charge of building track panels for the upcoming work on the upperloop. That team was able to build over 20 panels today out of the 50 needed. The other crew spent the day installing 70 feet of new track from Conner Siding down to the street crossing.