October 12 Workday
/With the Winter Meet only a week away, track crews were hard at work today getting a few projects completed. First task was to reconnect all the track going to the high bridge. All that is left to in that area to complete is to ballast and level the track. The second task was to remove the decking from the smaller bridge located near the high bridge. Since there was extra time today, the crew removed all the old bolts and repainted the bridge. On Saturday, the goal will be to install the new decking and track.