March 11 Workday
/Tennessee weather can change in a instant and on Saturday it did just that. With highs only in the upper 30s, club members came out to ballast the new track sections that were installed over the last few months. Two ballast trains were running non-stop for 4 hours and members were able to to get the first layer of ballast on about 50% of the new sections. Members were able to level and tamp these sections very effectively ( see photos below) and these sections will get one more layer to complete the job. Another ballast day is scheduled on March 25th to add more ballast and finish the sections still remaining we could not get to on this workday.