/With beautiful weather and a crew ready to work, the first project of the day was to install the new decking on the triple bridge. The first half of the day, crews secured the decking to the bridge and back filled the area so track could be installed. The second half of the day, crews installed panels of track and the two new switches for the crossover.
The main focus was to complete the inside track before the end of the day. This will allow a ballast train to begin work on the track from the high bridge down to this area. That track work was completed on the February 25 workday, but due to its location, could not be reached until this was completed. The next few work days (April 15 & 22) crews will continue the installation of the other two tracks on the bridges as well as complete the crossover track.