Depot Progress

Work on the New Passenger Depot has been going very well. In late July, the trenching was completed so power could be ran to the building. Once the trench was complete, the process of installing conduit could begin. Much of this work was done during the week, when members had extra time and weather permitted.

At the August 8th workday, members were back at the depot completing the electric conduit work. Junction boxes were installed and the conduit was buried in the trench. Additionally, more gravel was put down in preparation of the sidewalk install around the depot. Once the sidewalks are installed, the process of building the fencing will commence.